The full list of roadworks currently taking place throughout Redcar and Cleveland is available here.

The information supplied is provisional and may be subject to change.

Should you require any further information on the above roadworks please contact Angela Hoggarth on (01287) 612595 during office hours. Outside of office hours, please contact 01642 774774.

  • High Street / Normanby Road / Cleveland Street / West Road, Normanby

A temporary road closure will be in operation for Cleveland St and West Road and multi-way traffic lights will be in operation on Normanby Rd and High St, Normanby from 2nd April 2024 for up to 12 weeks to carry out Highway improvement works. A local diversion will be in operation, work to be carried out by Redcar and Cleveland Borough Council (Enquiries regarding this closure contact 01642455600, Engineer responsible for schemes Clive Allen).

  • Westgate, Guisborough

Multi-way traffic lights will be in operation from 21st February 2024 for up to 12 weeks to reconstruction the footway. Work to be carried out by Seymour Civil Engineering (Enquiries in case of signal failure contact 01914351557 or 07718489039).

  • Kirkleatham Lane, Redcar 

Two-way temporary traffic lights will be in operation from 27th March for up to 12 weeks to construct new entrance for new development. Work to be carried out by HMH Civils (Enquiries in case of signal failure contact 07894586899).

  • Guisborough Road (Waterfall roundabout to Margrove Rd), Charltons

Two-way temporary traffic lights will be in operation from 7th May 2024 for up to 7 days to carry out trail holes. Work to be carried out by Northumbrian Water (Enquiries in case of signal failure contact 07720611080).

  • Redcar Lane / Warwick Road, Redcar

Multi-way traffic lights will be in operation from 8th May 2024 to carry out emergency Utility repair and maintenance work. Work to be carried Northern Powergrid (Enquiries in case of signal failure contact 07870856323).

  • High Street, Eston

A temporary road closure will be in operation between Glaisdale Rd and Hutton Rd from 10th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

  • Albion Terrace / Greta Street, Saltburn

Multi-way traffic lights will be in operation from 8th May 2024 for up to 2 weeks to carry out Utility repair and maintenance works. Work to be carried out by Northern Gas Networks (Enquiries in case of signal failure contact 03700500792).

  • Park Lane, Grangetown

Two-way temporary traffic lights will be in operation from 15th May 2024 for up to 7 days to construct footway and carriageway. Work to be carried out by Moody Construction (Enquiries in case of signal failure contact 0191 416999)

  • Guisborough Road / Ormesby Bank, Nunthorpe

A temporary lane closure will be in operation around Swans corner roundabout on from 13th May 2024 for up to 3 days to carry repairs to defective surface apparatus. Work to be carried out by Esh Civils (Enquiries regarding this work contact 01642455600, Engineer responsible for schemes Clive Allen).

  • Brunel Road / Sotherby Road, South Bank

Multi-way traffic lights will be in operation from 13th May 2024 for up to 3 weeks to carry out Utility repair and maintenance works. Work to be carried out by Northern Gas Networks (Enquiries in case of signal failure 03700 500 792).

  • Esplanade, Redcar

Two-way temporary traffic lights will be in operation from 13th May 2024 for up to 10 days for carry out demolition of buildings. Work to be carried out by Hatton TM (Enquiries in case of signal failure 07948479278).

  • St. Patrick’s Road, Grangetown

A temporary road closure will be in operation from 13th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

  • Ennis Road, Dormanstown

A temporary road closure will be in operation from 13th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

  • Grewgrass Lane, New Marske

A temporary road closure will be in operation from 13th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

  • West Dyke Road, Redcar

Multi-way traffic lights will be in operation from 14th May 2024 for up to 3 days to carry out carriageway patching work. Work to be carried out by Redcar and Cleveland Borough Council (Enquiries in case of signal failure 07903712304)

  • Marske Road, Saltburn

Two-way temporary traffic lights will be in operation from 15th May 2024 for up to 2 weeks to carry out Utility repair and maintenance works. Works to be carried out by Northern Gas Networks (Enquiries in case of signal failure 03700 500 792)

  • Margrove Road, Boosebeck

Two-way temporary traffic lights will be in operation from 15th May 2024 for up to 7 days to carry out trail holes. Work to be carried out by Northumbrian Water (Enquiries in case of signal failure contact 07720611080).

  • Coach Road, Brotton

Stop/Go boards will be in operation from 15th May 2024 for up to 10 days to carry Utility asset works. Work to be carried out Equans on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 07584142547)

  • North Row, Lazenby

A temporary road closure will be in operation from 17th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

  • Lilac Close, Lazenby

A temporary road closure will be in operation from 17th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

  • Staintondale Avenue, Dormanstown

A temporary road closure will be in operation from 17th May 2024 for up to 3 days to carry out resurfacing of carriageway. Work will be undertaken by Tarmac on behalf of Redcar and Cleveland Borough Council (Enquiries regarding this work contact 01642 455600 Engineer responsible for scheme Russ Thompson).

Longbeck Road, Marske

A temporary overnight road closure will be in operation between 23:15hrs and 08:45hrs on 18th May 2024 to carry out work for rail purposes. Work to be carried out by Network Rail (Enquiries regarding this closure contact 01777 705053).

  • Brotton Road, Carlin How

Two-way temporary traffic lights will be in operation from 19th May 2024 for up to 1 day to carry out work to replace lamp column AC-43. Work to be carried out Equans on behalf of Redcar and Cleveland Borough Council (Enquiries in case of signal failure contact 07904102784).